India

Vizag gas leak: AP HC directs seizure of LG Polymers plant, prohibits directors from leaving India

The court also asked the government to inform it whether any permission was obtained to restart the company’s operations during the lockdown period

Photo Courtesy: social media
Photo Courtesy: social media 

The Andhra Pradesh High Court has ordered the government to seize the company premises of the LG Polymers chemical plant at Vishakapatnam, from where toxic amounts of styrene vapour had escaped on the intervening night of May 6 and 7, leading to several persons being hospitalised, besides causing environmental damage, legal news website BarandBench.com has reported.

While dealing with a batch of PILs filed in the wake of the tragedy, including a suo motu PIL initiated by the High Court on the morning of May 7, the Bench of Justices Jitendra Kumar Maheshwari and Lalitha Kanneganti have issued the following directions:

  • The premises of the company shall be completely seized;
  • No one should be allowed to enter into the premises including the Directors of the company;

Published: 25 May 2020, 1:43 PM IST

  • If a Committee, if any, appointed wants to inspect the premises, they are at liberty to. However, they shall put a note on the Register maintained at the gate of the Company regarding the said inspection and while returning, a note regarding the act down on the premises should also be noted.
  • None of the assets, movable or immovable, fixture, machinery and contents shall be allowed to be shifted without the leave of the court
  • The surrendered passports of the Company Directors should not be released without the leave of the Court.
  • The Company Directors are not allowed to go outside India without leave
  • The government should inform the court whether any permission was obtained to restart the company's operations during the lockdown period. If not, an action taken report on this aspect should be filed

Published: 25 May 2020, 1:43 PM IST

  • Given the grievance that multiple Committees over the issue have been appointed (by the NG, the Central Government and the State Government) the government authorities may apprise the court as to which Committee shall fulfil the purpose to answer all questions raised on the issue.

A compliance report on the following directions is to be filed before the court by the government authorities by May 26.

Published: 25 May 2020, 1:43 PM IST

Action taken reports silent on pertinent issues

The court on Friday also noted that the action taken reports filed by the state and Central government were silent on the following issues raised before the Court, i.e:

  • LG Polymers has been operating without a valid Environmental Clearance from the Ministry of Environment, Forests and Climate Change (MoEFCC);
  • The inhibitor concentration in the storage tank was not checked;
  • Refrigeration system was no working properly;
  • The radius of the vulnerable zone was extended up to 6.3km from the source;
  • There are several hospitals, educational institutions, places of worship, railway stations and airport within the vulnerable zone;
  • The bystander population should have been informed of the risk that they were in and trained in evacuation procedures in the event of an accident as per Manufacture, Storage and Import of Hazardous Chemicals Rules, 1989. But this has not been done;

Published: 25 May 2020, 1:43 PM IST

  • The siren/ alarm system did not function.

The matter has now been listed to be taken up next on May 28.

Published: 25 May 2020, 1:43 PM IST

Follow us on: Facebook, Twitter, Google News, Instagram 

Join our official telegram channel (@nationalherald) and stay updated with the latest headlines